ENGINEERING EXPLAINED / BATCH SCHEDULING
Find the clock that limits the plant.
Change reaction and filter occupancy to see why a faster reaction can leave batch output unchanged.
By Nathan, chemical engineer and co-founder of RARE Labs.
CHANGE THE CLOCKS
Faster chemistry can leave output unchanged.
Start-to-start interval
This two-equipment example repeats one recipe with one reactor and one filter. All times are illustrative hours.
What this example assumes.
The reactor is occupied by charging, reaction, transfer and its cleaning. Filter occupancy is filtration plus its own cleaning. A separate buffer can accept every transferred batch; capacity and blocking are omitted. There are no shared crews, utilities, cleaning skids, equipment failures or changeovers. Under those assumptions, the repeat interval is the larger of the two occupancy times.
A real plant can have more constraints. Equipment sharing, transfer timing, finite storage and overlapping demand for people or utilities can invalidate this simple maximum. Use the entire recipe and resource schedule before treating it as plant capacity.
Bring these to a focused review.
One representative recipe, equipment occupancy including turnaround, batch size, utility and crew demand, and the commitment the schedule must inform. Compare a changed recipe against the same constraints.
Sources: Intelligen: scheduling calculations and constraints · Intelligen: throughput and resource bottlenecks. The interactive example is an independent teaching model.